How long do Montreal building permits take? (2026 data)

22
median days
48.5
average days
23,716
permits (12 mo)
n/a
avg project value

Montreal building permits take a median of 19 days from application to issuance, with an average of 51 days, across 18,249 permits issued in the last 12 months. Simple residential alterations tend to land near or below the median; larger projects drive the average up.

What the gap between median and average means

A median of 19 days and an average of 51 days tells you the distribution is skewed: most permits are fast, but a smaller number of complex or commercial projects take significantly longer and pull the average up. For a homeowner applying for a renovation permit, the 19-day median is the more relevant number. For a developer with a larger project, the average is more predictive.

Submitting a permit application?

The Permit Compliance Audit checks your plans against zoning, building, and parking bylaws before you submit, so you catch the issues that trigger a resubmission cycle while they still cost nothing to fix. Free analysis first, $149 CAD one-time for the certified report.

See the Permit Compliance Audit, $149 CAD

Data notes for Montreal

The 18,249 permits in this dataset cover all permit types across the city over the trailing 12 months. The dataset includes application date and issuance date, so the figures here measure actual elapsed time, not an official target. Montreal does not publish a single processing-time target the way some other Canadian cities do.

Montreal permit activity at a glance

MetricValue
Median days to issuance22 days
Average days to issuance48.5 days
Permits issued (last 12 months)23,716
Average permits per month1,824
Average project valuen/a
Cross-city median (10 timing cities)29 days

How Montreal compares

The median across the 10 cities in our dataset that publish processing-time data is 29 days. Montreal sits 7 days faster than that benchmark. A wait time below it means permits here generally move faster; above it means the opposite. Either way, the spread between fast and slow categories within a single city is usually wider than the gap between cities, so the by-work-type table below matters more than any single headline number.

Permit activity by type of work in Montreal

Not all permits move at the same speed. Simple alterations clear far faster than new-building applications. Here is how the most common work types in Montreal broke down over the last 12 months:

Type of workPermitsMedian daysAvg days
Permis neige - 1 stationnement - 1 an171711.5
Réfection de la toiture par la mise en place de l'asphalte et gravier blanc. Aucuns travaux de structure.11935
Réfection de la toiture par la mise en place d'une membrane blanche. Aucuns travaux de structure.11635.1
REMPLACER LA MEMBRANE DE LA TOITURE PAR UNE NOUVELLE MEMBRANE BLANCHE7412
Toit, plat, remplac., en total, gravier blanc68538.8
CERTIFICAT-MISE AUX NORMES D'UNE PISCINE CREUSÉE5578126.2
Type2 -À l'extérieur, remplacer la porte d'issue de secours et une fenêtre dans la même ouverture, remplacement localisé de la maçonnerie et travaux de rejointement. À l'intérieur, réaménagement de la salle de rangement. Réfection de la toiture par la mise en place de l'asphalte et du gravier blanc. Le tout tel que les plans. Aucun travaux de structure.554443.9
RÉFECTION COMPLÈTE DU REVÊTEMENT DE LA TOITURE (TOIT BLANC)5276.4
Remplacer le revêtement de toiture en totalité par membrane blanche. Aucuns travaux de structure. Tel que document approuvé.4959.2
Type1-À l'extérieur, remplacer la porte d'issue de secours et une fenêtre dans la même ouverture, remplacement localisé de la maçonnerie et travaux de rejointement. À l'intérieur, réaménagement la salle électrique. Réfection de la toiture par la mise en place de l'asphalte et du gravier blanc. Le tout tel que les plans. Aucun travaux de structure.434746.7
REMPLACER LA MEMBRANE DE LA TOITURE PAR UNE NOUVELLE MEMBRANE D'ASPHALTE RECOUVERTE DE GRAVIER DE MARBRE BLANC3011.5
Réfection de la toiture par la mise en place de gravier blanc. Aucuns travaux de structure.2844

Permit volume trend

Montreal issued 23,716 permits over the trailing 12 months. The busiest single month was Jul 2026 (3,480 permits). Volume drives wait times: months with a surge in applications tend to push processing times up as review staff work through the backlog.

What drives building permit wait times

Permit processing time is rarely about a single step. The biggest levers are:

How to read these benchmarks

These are permit-volume and application-to-issuance timing benchmarks, they measure how long permits that were issued took to get there. They are not approval rates: the underlying dataset has no approval-versus-denial field, so we never report rejection percentages. Use the median as your realistic planning number, the average as your worst-case buffer, and the by-work-type table to set expectations for your specific project.The single best way to stay on the fast end is to submit a complete, compliant application the first time.

Frequently asked questions

How long does a Montreal building permit take in 2026?

Based on 18,249 permits issued over the last 12 months, the median time from application to issuance in Montreal is 19 days and the average is 51 days. Simple residential work tends to land near or below the median; larger or commercial projects drive the average higher. The spread reflects the range of project types Montreal processes, from minor interior alterations to major new construction.

What types of projects need a permit in Montreal?

Most work that changes a building's structure, exterior, systems, or use requires a permit in Montreal. This includes additions, new construction, structural alterations, changes to electrical or plumbing systems, pool installation, and changes of use. Cosmetic interior work that does not affect structure or systems typically does not require a permit, but the city's permit guide is the authoritative reference for a specific project.

Check a Montreal permit for free

See every permit on record for any Montreal address, free. The full history report is $29 if you want it.

Check a Montreal permit, free

Permit wait times by city

Source: Van Permit Audit national dataset

Related guides

See how Montreal compares.

Browse permit volumes, declared values, and wait times for cities across Canada in our national permit dataset. Real municipal data, not estimates.

Compare Canadian cities

Check a Montreal permit for free

See every permit on record for any Montreal address, free. The full history report is $29 if you want it.

Check a Montreal permit, free

Planning a project in Montreal?

Before you submit in Montreal, run your plans through the Permit Compliance Audit: an AI-powered check against zoning, building, and parking bylaws that flags the issues reviewers send back for resubmission. Free analysis first, $149 CAD one-time for the certified report.

See the Permit Compliance Audit, $149 CAD

Compare other cities

See all 31 cities·Back to the blog

Source: Wolf Codes permit dataset of over 3.1 million Canadian building permits. Volume and timing figures on this page cover the trailing 12 months, analysed August 2026. Permit-volume and (where available) application-to-issuance timing benchmarks from the Wolf Codes permit dataset. The data has no approval/denial column, so these are NOT approval rates — they measure how many permits were issued, their declared value, and how long issued permits took where a processing-time field is published. Only cities with at least 50 qualifying permits are reported.