Data Report

Canadian Building Permit Approval Times

3.1 million permits. 32 cities. 2018 to 2025. Here is what the numbers say about how long it actually takes to get a building permit in Canada, neighbourhood by neighbourhood.

Published by Van Permit Audit. Data source: municipal open data portals. Verified via BigQuery, 2026-07-02.

Key findings

86 days

Vancouver median (all permit types)

50,496 permits, 2018-2025

210 days

Vancouver new building permit median

7+ months from application to approval

4x gap

Within Vancouver: West End (35 days) vs Victoria-Fraserview (138 days)

201 days

Vancouver laneway home permit average

2,244 permits since 2022

13 days

Kelowna median vs Vancouver's 86

Both cities in BC

3.1M

Permits tracked across 32 Canadian cities

$443.6B in declared project value

By the numbers

·

The median Vancouver building permit takes 86 days. In Victoria-Fraserview, expect 138 days. In West End, just 35. That is a 4x gap within one city.

·

Vancouver new building permits took a median of 210 days from 2018 to 2025, more than seven months from application to approval.

·

2023 was Vancouver's worst year on record for permit processing: 169 days average. By 2025, it improved to 116 days, but still above the pre-pandemic 2019 baseline of 121 days.

·

Laneway home permits in Vancouver averaged 201 days from 2022 to 2025, based on 2,244 permits with "laneway" in the project description.

·

Kelowna's median permit approval time is 13 days. Vancouver's is 86 days. Both cities are in BC.

·

In Vancouver, addition and alteration permits (most homeowner renovations) took a median of 47 days. New buildings: 210 days. Demolitions: 179 days.

·

BC declared $6.75 billion in building permit project value in 2025, up from $3.46 billion in 2019.


Avoid the revision cycle that adds months

Most Vancouver delays start with an incomplete submission. A pre-submission audit catches bylaw gaps before the city does.

Get a $149 Readiness Audit

Section 1

The national picture: city-by-city median approval times

Approval-time records (the permitelapseddays field populated): 710,981 permits across 6 cities with sufficient data quality for this analysis.

CityProvinceMedian DaysPermits with elapsed-day data
VancouverBC8650,496
TorontoON34176,630
MontrealQC24392,623
St. CatharinesON1917,466
KelownaBC1351,766
Thunder BayON1412,178

Methodological note: Median (PERCENTILE_CONT) is used throughout because a small number of stalled permits inflate averages. Vancouver median 86 days; average 135 days. Cross-city comparisons are directional; elapsed-day definitions vary by municipality.

Explore the full dataset by city and permit type on the BC Building Permits data page.


Section 2

Vancouver deep dive

Approval times by neighbourhood (median days)

NeighbourhoodMedian DaysPermits
Victoria-Fraserview1382,130
Sunset1362,729
Hastings-Sunrise1313,085
Oakridge1311,296
Kerrisdale1301,331
South Cambie128925
Killarney1281,659
Dunbar-Southlands1282,525
Riley Park1272,411
West Point Grey1261,526
Renfrew-Collingwood1253,239
Kensington-Cedar Cottage1223,875
Shaughnessy114956
Arbutus Ridge1131,291
Marpole1051,856
Grandview-Woodland1001,752
Kitsilano772,549
Mount Pleasant671,962
Strathcona641,051
Fairview422,261
Downtown367,283
West End352,423

Source: 50,496 Vancouver permits with approval-time data, 2018-2025. PERCENTILE_CONT(0.5) by neighbourhood.

Approval times by type of work

Type of WorkMedian DaysAvg DaysPermits
New Building21024611,615
Demolition / Deconstruction1792086,887
Salvage and Abatement59786,612
Addition / Alteration478124,870
Temporary Building / Structure825451

Laneway home permits: 201 days average

Vancouver laneway home permits averaged 201 days from application to approval, based on 2,244 permits with "laneway" in the project description, issued from 2022 to present. This represents a significant wait even against Vancouver's already-slow citywide baseline.

Vancouver year-over-year trend

YearAvg Approval DaysPermits Issued
20181356,721
20191215,559
20201374,383
20211295,016
20221585,924
20231694,647
20241264,871
20251165,120

2023 was Vancouver's worst year on record in this dataset at 169 days average. The improvement to 116 days in 2025 is real, but still above the pre-pandemic 2019 baseline of 121 days.


Section 3

BC province-wide trends

YearBC Avg DaysBC PermitsBC Declared Value
20181138,609$4.76B
20191007,484$3.46B
20201056,238$4.33B
2021987,564$3.83B
20221297,932$7.27B
20231376,313$6.81B
20241066,338$4.61B
20251016,598$6.75B

Source: Van Permit Audit dataset, province='BC', PERCENTILE_CONT / AVG by issue year, queried 2026-07-02.


Section 4

What causes building permit delays in Vancouver?

1.

Incomplete submissions are cited as a leading cause by City staff and industry groups. Applications missing required drawings, engineer stamps, Step Code compliance documentation, or bylaw analysis go back to the applicant for correction before a plan checker begins substantive review.

2.

Bylaw complexity. Vancouver Building By-law 2025, Zoning By-law, and Parking By-law 6059 require simultaneous compliance. South and east RS-1 zoning neighbourhoods show the longest wait times in the dataset.

3.

Plan checker capacity. The 2022 to 2023 surge (peak 7,932 BC permits in 2022) coincided with the worst approval times. The dataset shows the correlation clearly.

4.

Revision cycles. The gap between Vancouver's average (135 days) and median (86 days) reflects a long tail of projects stuck in multiple revision rounds. Each revision restarts the clock.

The single highest-leverage action

Before submitting a Vancouver permit application: ensure every required document is complete and every bylaw item is addressed. A pre-submission audit catches these issues before the city does, avoiding the revision cycle that adds months. VPA's $149 readiness audit checks 12+ compliance categories against the current Vancouver Building By-law, Zoning By-law, and Parking By-law.


FAQ

Common questions

Do I need a permit for a deck in Vancouver?

In most cases, yes. Decks above grade typically require a building permit in Vancouver under the Vancouver Building By-law 2025. Check your specific project against current bylaw requirements before starting work.

What happens if I renovate without a permit in Vancouver?

Unpermitted work surfaces during property sale. Buyers' lawyers routinely search permit history through the City's open permit database. Retroactive permits often require opening finished walls for inspection. The City can issue Stop Work Orders for active unpermitted construction. Mortgage lenders may decline financing on properties with known unpermitted additions.

What do I need to submit a building permit in Vancouver?

Standard requirements: completed application, site plan, floor plans (existing and proposed), elevations, structural drawings (engineer-stamped for structural work), energy compliance documentation (BC Step Code), and permit fees. The most common cause of delay is missing bylaw compliance items caught during plan review.

How do I estimate my permit timeline?

Use the neighbourhood and work-type data in this report as a baseline. Addition and alteration permits (most renovations) have a median of 47 days citywide; new buildings run 210 days. South and east Vancouver neighbourhoods tend to be slower. The single highest-leverage action is ensuring your submission is complete before you file.


Cite this data

Van Permit Audit (2026). Canadian Building Permit Approval Times: A City-by-City Data Report, 2018-2025. Retrieved from https://vanpermitaudit.ca/data

Dataset reference: 3,114,538 Canadian building permit records across 32 cities, 2018-2025. Approval-time data available for 710,981 records. Source: municipal open data portals.

Press and data inquiries: adam@wolfcodes.ca

Dataset coverage notes

  • Total permits: 3,114,538 across 32 cities (BigQuery verified 2026-07-06)
  • Cities with elapsed-day data used in this analysis: Vancouver, Toronto, Montreal, Kelowna, St. Catharines, Thunder Bay
  • Date range: 2018 to 2025
  • Source: Municipal open data portals
  • Exclusions: permitelapseddays IS NULL, less than or equal to 0, or 2000 or more (data quality filter)
  • Methodology: PERCENTILE_CONT(0.5) for all median statistics. Averages noted where used.

Estimate your specific timeline

Select your neighbourhood and work type for a personalised estimate based on these numbers.

Open estimator

Avoid the revision cycle that adds months