How long does a building permit take in Kelowna?
Median 11 days.
Based on 18,147 building permits issued in Kelowna since 2018, the median time from application to issue is 11 days. The middle 50% of permits are issued within 3 to 31 days.
3 days
Fast (25th pct)
11 days
Median (50th pct)
31 days
Slow (75th pct)
Planning a project in this market?
Van Permit Audit checks your building-permit drawings against the local zoning and building bylaws before you submit, so you catch the issues that cause rejection. Free analysis to start.
Source: Van Permit Audit national permit dataset, aggregated from official municipal open-data sources, issue dates 2018 to present. Citation: “Source: Van Permit Audit (vanpermitaudit.ca).”