VanPermitAudit/ BlogCheck an Address, $29
Bylaws Explained

Why BC Permit Applications Get Sent Back: The 7 Most Common Rejection Reasons

By Adam Kurtoglu, Founder, Wolf Codes Inc.

Bylaw References

District of North Saanich Building and Plumbing Bylaw No. 1150, s. 5.17 and s. 5.18City of Vancouver Protection of Trees By-law No. 9958District of Oak Bay Tree Protection Bylaw No. 4742

Most BC building permit applications that come back to the applicant are not rejected on the design. They are returned at the counter because a document on the municipality’s own list is missing, out of date, or not signed by the right person. The rules for this are written down, in public, before you apply.

The District of North Saanich says it plainly in its Building Permit Application Information package: “Applications for building permits will not be accepted until all the information is provided.” The same package adds, for the servicing review, that “incomplete submissions will not be reviewed and the applicant will be notified by District Administrative staff to resubmit.”

That is the whole mechanism. Below are the seven gaps that trigger it most often, with the published source for each. Requirements differ from one municipality to the next, so always read your own city’s checklist. The pattern, though, repeats across BC.

1. The certificate of title is missing or out of date

Most BC municipalities want a recent certificate of title with the application, including copies of everything registered against it. North Saanich asks for a “Recent Certificate of Title (not more than 30 days old) including copies of all charges,” and spells out that charges means covenants, easements and statutory rights of way (Building Permit Application Information package).

A title pulled four months ago during your financing is usually too old. Pull a fresh one the week you submit, and read the charges: a covenant or right of way across the part of the lot you planned to build on changes the drawing, not just the paperwork.

Submitting a permit application?

The Permit Compliance Audit checks your plans against zoning, building, and parking bylaws before you submit, so you catch the issues that trigger a resubmission cycle while they still cost nothing to fix. Free analysis first, $149 CAD one-time for the certified report.

See the Permit Compliance Audit, $149 CAD

2. The survey is a sketch, not a sealed survey

A site plan drawn by a designer is not a survey. Where a municipality requires a survey sealed by a BC Land Surveyor, an unsealed sketch is returned at intake even when every dimension on it happens to be correct. The seal is the point: it is what makes the lot lines, grades and setback measurements an attested record rather than an assumption.

Oak Bay’s new house building permit checklist is a good example of the document list a municipality publishes up front for exactly this reason.

3. The drawing set is incomplete

A complete, scaled set for new work means a site plan, floor plans, elevations of every side, and building sections. Elevations are where sets most often fall short. A front-only elevation set is a partial set, and it is returned as one.

North Saanich’s Building and Plumbing Bylaw No. 1150 lists what the drawings have to show, including “a cross section through the building or structure illustrating foundations, drainage, ceiling heights and construction systems” and “elevations of all sides of the building or structure showing finish details, roof slopes, windows, doors, and finished grade.”

4. Professional seals and letters of assurance are missing

This is the gap that surprises homeowners most, because it is conditional. A building official can require that drawings be sealed by a registered professional, and that construction happen under that professional’s supervision, when the site conditions, size or complexity of the work call for it. North Saanich Bylaw 1150 s. 5.17.1 says the building official may require this “as a condition precedent to the issuance of a building permit.”

Two specific triggers show up again and again:

Where letters of assurance are required, Schedule D is the registered professional’s proof of liability insurance, and Schedules C-A or C-B come later, before the occupancy permit. If more than one professional is involved, Schedule A coordinates them.

Check a Vancouver permit for free

See every permit on record for any Vancouver address, free. The full history report is $29 if you want it.

Check a Vancouver permit, free

5. No energy report, or a report at the wrong step

BC new residential construction needs energy compliance documentation at application, not after. North Saanich’s own BC Energy and Zero Carbon Step Codes handout sets Step Level 3 for buildings in the District, with guest cottages excepted.

Two mistakes cause the resubmission: no report at all, and a report written to a lower step than the municipality requires. Both read the same way to a plan checker, and both cost a cycle.

6. No arborist report where a protected tree is on site

Tree protection is municipal, and the trigger diameter is different in every bylaw. Vancouver’s Protection of Trees By-law No. 9958 protects trees from 20 cm in trunk diameter. Oak Bay’s Tree Protection Bylaw No. 4742 sets a higher general threshold and protects named native species, Garry oak among them, at a much smaller size.

The practical risk is that a threshold you remember from another city does not apply to your lot. Check the number in your own municipality’s bylaw before the footprint is fixed, because a tree protection zone can take the buildable area you were counting on.

7. Servicing, stormwater and parking are not shown

Engineering reviews the same submission the building department does, and it is looking for different things on the site plan. North Saanich’s package lists them explicitly: existing and proposed water lines, wells, septic fields, sanitary and storm drain facilities with sizes and minimum slopes; natural and finished grades; the high water mark, top of bank and any watercourse or riparian area within 30 m; and the stormwater management system. It also warns that existing municipal services may need to be brought up to current standards before a permit is issued.

Off-street parking is the other quiet one. A suite or an added unit usually adds a required stall, and the stall has to fit and be usable, not just appear on the plan.

What a returned application actually costs

Not a fee, usually. Time. Each resubmission puts you back in the queue behind everything filed since, and that queue is the part of the timeline you do not control. The documents above are the part you do. Our write-up on how long a building permit takes in Metro Vancouver shows how the published review targets assume a complete application as the starting line.

If you want a second read of your package against the bylaws before you submit, that is what the Permit Readiness Review is for. The analysis is free, and the written report is $149 CAD one time.

Frequently asked questions

Does a returned application mean my project was refused?

No. In most cases nothing has been judged yet. The application was not accepted as complete, so the review has not started. You add the missing document and resubmit.

Which document is most often missing?

In published checklists the recurring items are the recent certificate of title, a surveyor sealed survey, complete elevations, and the energy compliance report. Which one bites you depends on your project type and your municipality’s list.

Do I need an engineer for a small renovation?

Not always. It depends on the scope. A building official can require a registered professional where site conditions, size or complexity warrant it, and some triggers are fixed: manufactured products such as trusses need an engineering Schedule B, and a retaining wall over one metre needs professional design and field review in North Saanich.

How recent does my certificate of title have to be?

Check your own municipality. North Saanich asks for one no more than 30 days old, including copies of all charges. Other BC municipalities publish a similar window, so pull a fresh title close to your submission date rather than reusing an older one.

Permit wait times by city

Source: Van Permit Audit national dataset

Related guides

Check a Vancouver permit for free

See every permit on record for any Vancouver address, free. The full history report is $29 if you want it.

Check a Vancouver permit, free

Submitting a permit application?Run a compliance check first

Get the free Vancouver Permit Pre-Submission Checklist

The 12-point checklist that catches the issues that send permit applications back for resubmission, plus wait-time alerts for your city. One email to confirm, unsubscribe anytime in one click.

We email a single confirmation link (CASL double opt-in). No spam, one-click unsubscribe on every email.

Sources & Further Reading

All stories referenced are from public news reporting and verified sources. Short quotes are used under fair dealing for commentary and analysis purposes. Bylaw citations are drawn directly from the City of Vancouver Zoning and Development By-law and Vancouver Building By-law 2025, publicly available at vancouver.ca.

Submitting a permit application?

The Permit Compliance Audit checks your plans against zoning, building, and parking bylaws before you submit, so you catch the issues that trigger a resubmission cycle while they still cost nothing to fix. Free analysis first, $149 CAD one-time for the certified report.

See the Permit Compliance Audit, $149 CAD