There is no single Metro Vancouver permit timeline, and most of the region’s cities do not publish one. Two do give you something solid: Vancouver, through its own issued-permit records, and Surrey, through a published target. For the rest, the honest answer is that no public number exists, so this post gives you the process instead of inventing one.
Here is what the data supports, city by city.
Vancouver: real elapsed time, by work type
Vancouver publishes dates on its issued permits, so elapsed time can be measured rather than estimated. Across 6,730 Vancouver permits in our dataset over a trailing 12 month window (snapshot 2026-08-24), the median from application to issuance is 65 days and the average is 114.9 days.
That gap between 65 and 114.9 is the thing to understand before you plan anything. A minority of applications take far longer than typical and pull the average up. Use the median for planning, then build in room.
The city-wide number is still too blunt to budget against, because work type dominates:
| Type of work | Median days | Average days | Permits |
|---|---|---|---|
| Temporary Building / Structure | 17 | 24.4 | 68 |
| Addition / Alteration | 33 | 66.6 | 3,791 |
| Salvage and Abatement | 64 | 141.5 | 176 |
| Demolition / Deconstruction | 105 | 144.1 | 1,072 |
| New Building | 173 | 210.3 | 1,622 |
If you are renovating, the line that applies to you is Addition / Alteration: a 33 day median. If you are building new, it is 173 days, which is close to six months in the queue before construction starts. And if your project needs a demolition first, that is its own permit at a 105 day median, running before or alongside the new building one.
One limit on all of this: these records carry application and issuance dates, with no approval or denial field. Nothing here is an approval rate or a rejection rate. It measures how long issued permits took.
Submitting a permit application?
The Permit Compliance Audit checks your plans against zoning, building, and parking bylaws before you submit, so you catch the issues that trigger a resubmission cycle while they still cost nothing to fix. Free analysis first, $149 CAD one-time for the certified report.
See the Permit Compliance Audit, $149 CADSurrey: a published target, and a faster actual
Surrey is the one Metro Vancouver city with a clear published commitment. Its permitting timelines page sets a target of 10 weeks for a residential building permit covering new single-family homes and duplexes, and the City’s own dashboard showed the current average running faster than that, at 4.1 weeks, when we read the page on 2026-08-22 (the page itself was last updated 2026-08-17).
Treat the 10 weeks as the commitment and the 4.1 weeks as a current condition that can change with volume. Both assume a complete application.
Burnaby, Richmond, New Westminster and Maple Ridge: no published target
We checked each city’s own permit pages on 2026-08-22. None of these four publishes an overall building permit processing-time target:
- Burnaby. No overall target on the new home construction page. The one published figure we found is narrower and earlier in the sequence: complete Engineering Pre-Application submissions for new home construction take about 15 business days to review.
- Richmond. No processing-time target on the Building Approvals FAQ.
- New Westminster. No processing-time target published on its permit pages.
- Maple Ridge. No processing-time target on its residential permits page.
Anyone quoting you a confident week count for these cities is estimating. What we can tell you is the sequence.
Check a Vancouver permit for free
See every permit on record for any Vancouver address, free. The full history report is $29 if you want it.
Check a Vancouver permit, freeThe process, without the numbers
The steps are consistent across BC municipalities, and the District of North Saanich sets them out unusually clearly in its Building Permit Application Information package. The stages:
- Intake and acceptance. Your application is checked for completeness. The North Saanich package is explicit that applications “will not be accepted until all the information is provided.” Until acceptance, your clock has not started.
- Queue. Accepted applications are “processed in the order that they are received.” Filing earlier does not jump the queue; filing complete is what gets you into it.
- Review. Staff review the plans for compliance with the municipality’s bylaws and the BC Building Code. In cities with a separate engineering or servicing review, that runs too, which is the stage Burnaby’s 15 business day figure describes.
- Preparation and conditions. Where the project needs a development variance permit, a covenant or rezoning, that is a separate approval with its own timeline sitting on top of the building permit.
- Issuance. The permit is prepared and issued once outstanding fees and deposits are paid. In North Saanich those can include the balance of permit fees, engineering fees and deposits, off-site costs, a contractor’s liability insurance certificate, and development cost charges.
So “how long does a permit take” is really five clocks, and only some of them are the city’s.
What you actually control
North Saanich names five factors that move its review time: the volume of applications, the complexity of the project, the accuracy of the application, whether a development variance permit, covenant or rezoning is required, and whether the plans comply with the zoning and other bylaws including the BC Building Code.
Read that list again and sort it. Volume is the city’s. Complexity is mostly set by your project. Accuracy and compliance are yours, and so is whether you need a variance.
Which gives you four levers:
- File complete. An application that is not accepted is not in the queue. Every missing document is dead time, not review time.
- File accurate. A number that does not survive checking sends the package back, and a resubmission returns you to the end of the queue rather than the point where you left off.
- Design to the standard, not to a hoped-for relaxation. If your footprint only works with a variance, you have added an approval with its own schedule.
- Sequence the related permits. A demolition and a new building are two permits with two timelines. Plan them as two.
The written-down version of this is our list of the seven document gaps that get applications returned: why BC permit applications get sent back. If you would rather have your own package checked against the bylaws before you file, that is the Permit Readiness Review, and the first analysis is free.
Frequently asked questions
How long does a Vancouver building permit take?
Across 6,730 Vancouver permits over a trailing 12 months, the median was 65 days from application to issuance and the average 114.9 days. By work type, additions and alterations ran a 33 day median and new buildings a 173 day median.
Which Metro Vancouver city is fastest?
The data does not support naming one. Only Vancouver publishes dates we can measure, and only Surrey publishes a target. The other cities we checked publish no processing-time figure, so a ranking would be guesswork.
Does calling the city speed up my permit?
No evidence of that, and the published process says applications are handled in the order received. The documented levers are completeness and accuracy at submission.
Why is the average so much higher than the median?
A small number of complex applications take far longer than typical and drag the mean upward. For Vancouver the median of 65 days describes the usual experience better than the 114.9 day average.