How Long a Building Permit Takes in Metro Vancouver, and What You Control

By Adam Kurtoglu, Founder, Wolf Codes Inc.

There is no single Metro Vancouver permit timeline, and most of the region’s cities do not publish one. Two do give you something solid: Vancouver, through its own issued-permit records, and Surrey, through a published target. For the rest, the honest answer is that no public number exists, so this post gives you the process instead of inventing one.

Here is what the data supports, city by city.

Vancouver: real elapsed time, by work type

Vancouver publishes dates on its issued permits, so elapsed time can be measured rather than estimated. Across 6,730 Vancouver permits in our dataset over a trailing 12 month window (snapshot 2026-08-24), the median from application to issuance is 65 days and the average is 114.9 days.

That gap between 65 and 114.9 is the thing to understand before you plan anything. A minority of applications take far longer than typical and pull the average up. Use the median for planning, then build in room.

The city-wide number is still too blunt to budget against, because work type dominates:

Type of workMedian daysAverage daysPermits
Temporary Building / Structure1724.468
Addition / Alteration3366.63,791
Salvage and Abatement64141.5176
Demolition / Deconstruction105144.11,072
New Building173210.31,622

If you are renovating, the line that applies to you is Addition / Alteration: a 33 day median. If you are building new, it is 173 days, which is close to six months in the queue before construction starts. And if your project needs a demolition first, that is its own permit at a 105 day median, running before or alongside the new building one.

One limit on all of this: these records carry application and issuance dates, with no approval or denial field. Nothing here is an approval rate or a rejection rate. It measures how long issued permits took.

Submitting a permit application?

The Permit Compliance Audit checks your plans against zoning, building, and parking bylaws before you submit, so you catch the issues that trigger a resubmission cycle while they still cost nothing to fix. Free analysis first, $149 CAD one-time for the certified report.

See the Permit Compliance Audit, $149 CAD

Surrey: a published target, and a faster actual

Surrey is the one Metro Vancouver city with a clear published commitment. Its permitting timelines page sets a target of 10 weeks for a residential building permit covering new single-family homes and duplexes, and the City’s own dashboard showed the current average running faster than that, at 4.1 weeks, when we read the page on 2026-08-22 (the page itself was last updated 2026-08-17).

Treat the 10 weeks as the commitment and the 4.1 weeks as a current condition that can change with volume. Both assume a complete application.

Burnaby, Richmond, New Westminster and Maple Ridge: no published target

We checked each city’s own permit pages on 2026-08-22. None of these four publishes an overall building permit processing-time target:

Anyone quoting you a confident week count for these cities is estimating. What we can tell you is the sequence.

Check a Vancouver permit for free

See every permit on record for any Vancouver address, free. The full history report is $29 if you want it.

Check a Vancouver permit, free

The process, without the numbers

The steps are consistent across BC municipalities, and the District of North Saanich sets them out unusually clearly in its Building Permit Application Information package. The stages:

  1. Intake and acceptance. Your application is checked for completeness. The North Saanich package is explicit that applications “will not be accepted until all the information is provided.” Until acceptance, your clock has not started.
  2. Queue. Accepted applications are “processed in the order that they are received.” Filing earlier does not jump the queue; filing complete is what gets you into it.
  3. Review. Staff review the plans for compliance with the municipality’s bylaws and the BC Building Code. In cities with a separate engineering or servicing review, that runs too, which is the stage Burnaby’s 15 business day figure describes.
  4. Preparation and conditions. Where the project needs a development variance permit, a covenant or rezoning, that is a separate approval with its own timeline sitting on top of the building permit.
  5. Issuance. The permit is prepared and issued once outstanding fees and deposits are paid. In North Saanich those can include the balance of permit fees, engineering fees and deposits, off-site costs, a contractor’s liability insurance certificate, and development cost charges.

So “how long does a permit take” is really five clocks, and only some of them are the city’s.

What you actually control

North Saanich names five factors that move its review time: the volume of applications, the complexity of the project, the accuracy of the application, whether a development variance permit, covenant or rezoning is required, and whether the plans comply with the zoning and other bylaws including the BC Building Code.

Read that list again and sort it. Volume is the city’s. Complexity is mostly set by your project. Accuracy and compliance are yours, and so is whether you need a variance.

Which gives you four levers:

The written-down version of this is our list of the seven document gaps that get applications returned: why BC permit applications get sent back. If you would rather have your own package checked against the bylaws before you file, that is the Permit Readiness Review, and the first analysis is free.

Frequently asked questions

How long does a Vancouver building permit take?

Across 6,730 Vancouver permits over a trailing 12 months, the median was 65 days from application to issuance and the average 114.9 days. By work type, additions and alterations ran a 33 day median and new buildings a 173 day median.

Which Metro Vancouver city is fastest?

The data does not support naming one. Only Vancouver publishes dates we can measure, and only Surrey publishes a target. The other cities we checked publish no processing-time figure, so a ranking would be guesswork.

Does calling the city speed up my permit?

No evidence of that, and the published process says applications are handled in the order received. The documented levers are completeness and accuracy at submission.

Why is the average so much higher than the median?

A small number of complex applications take far longer than typical and drag the mean upward. For Vancouver the median of 65 days describes the usual experience better than the 114.9 day average.

Permit wait times by city

Source: Van Permit Audit national dataset

Related guides

Check a Vancouver permit for free

See every permit on record for any Vancouver address, free. The full history report is $29 if you want it.

Check a Vancouver permit, free

Submitting a permit application?Run a compliance check first

Get the free Vancouver Permit Pre-Submission Checklist

The 12-point checklist that catches the issues that send permit applications back for resubmission, plus wait-time alerts for your city. One email to confirm, unsubscribe anytime in one click.

We email a single confirmation link (CASL double opt-in). No spam, one-click unsubscribe on every email.

Sources & Further Reading

All stories referenced are from public news reporting and verified sources. Short quotes are used under fair dealing for commentary and analysis purposes. Bylaw citations are drawn directly from the City of Vancouver Zoning and Development By-law and Vancouver Building By-law 2025, publicly available at vancouver.ca.