“My designer handles the permit” is one of the most common things homeowners say before a renovation, and it is not how BC building bylaws are written. The bylaw puts the responsibility on the owner by name, and it says so in the same sentence as the words “full responsibility.”
What follows is quoted from one municipality’s building bylaw, the District of North Saanich Building and Plumbing Bylaw No. 1150. The structure of these clauses is common across BC building bylaws, so read yours. The wording here is one city’s, and it is clear enough to be worth reading in full.
The short answer: the owner, or the owner’s agent
Bylaw 1150 s. 1.7.1 begins: “It shall be the full responsibility of the owner or his agent to ensure all construction complies [with] the Building Code, this Bylaw, all other bylaws of the District and other applicable enactments respecting safety.”
Then it closes the obvious escape routes: “Neither the issuance of a permit under this Bylaw, the review of drawings, plans and specifications, nor inspections made by the Building Official, shall relieve the owner or his agent from this responsibility.”
Note the phrase “or his agent.” The bylaw defines an agent as “a person, firm, company or corporation representing the owner by written designation or contract, and includes a hired tradesman or contractor who may be granted permits for work within the limitations of his licence.” So a contractor who pulls the permit is acting as your agent. That is a real transfer of responsibility, and it depends on a written designation or contract. Verbally assuming your builder “has it” is not that.
Submitting a permit application?
The Permit Compliance Audit checks your plans against zoning, building, and parking bylaws before you submit, so you catch the issues that trigger a resubmission cycle while they still cost nothing to fix. Free analysis first, $149 CAD one-time for the certified report.
See the Permit Compliance Audit, $149 CADWhat the city is explicitly not responsible for
This is the part most people have never read, and it reframes the whole question.
No duty of care. Section 1.4 states the bylaw “does not create any duty of care whatsoever on the District, the Council members, the Building Official, or any employees or agents of the District” in respect of issuing a permit, reviewing the drawings, making inspections or failing to make them, and enforcing or failing to enforce the Building Code.
No cause of action. Section 1.5 says that neither a failure to enforce, nor inadequate enforcement, nor any error or omission in issuing a permit, reviewing plans or inspecting, “shall give rise to a cause of action in favor of any person whomsoever, including the owner.”
No warranty. Section 1.6 is the one to remember: issuing a permit, reviewing the drawings and inspecting the work do not “in any way constitute a representation, warranty or statement that the Building Code or this Bylaw has been complied with and no person shall rely on any of the above listed matters as establishing compliance.”
A stamped permit is permission to build. It is not a certificate that your drawings are right.
Where the designer’s responsibility is actually defined
The bylaw does not leave professional responsibility vague. It attaches it to named documents.
Section 5.17.1(a) lets the building official require, as a condition of issuing a permit, that drawings, specifications and plot plans be “prepared, sealed and signed by” a Registered Professional, and that construction be “carried out under the supervision of” one, where the site conditions, size or complexity of the work warrant it.
Section 5.17.1(b) goes further: the official may require that professional to confirm in writing that the submissions were prepared in accordance with the Building Code, and “to sign an undertaking that he will be responsible for the supervision of construction to completion.”
That is the mechanism. A professional’s responsibility is created by a signature on a defined instrument, and the instruments are the BC Building Code’s letters of assurance:
- Schedule A coordinates the work when more than one professional is involved. The District’s application package asks for it in exactly that case.
- Schedule B is the design and field review assurance. Section 5.18.1 refers to it as the form “referred to in Subsection 2.2.7 Division C of the Building Code.” The application package names a concrete trigger: any manufactured products such as trusses, I joists or manufactured beams.
- Schedules C-A and C-B come at the end. Section 5.18.2 requires the owner to provide them before an occupancy permit is issued where letters of assurance were required.
- Schedule D is the professional’s proof of professional liability insurance, required under s. 5.18.3 whenever letters of assurance are given.
There is one place where the bylaw does not wait to be asked. Section 5.19: “A registered professional shall undertake the design and conduct field reviews of the construction of a retaining wall greater than 1 meter in height.” No discretion, no trigger.
Check a Vancouver permit for free
See every permit on record for any Vancouver address, free. The full history report is $29 if you want it.
Check a Vancouver permit, freeWhere the builder’s responsibility is defined
Two instruments matter on the construction side.
The first is the agency relationship above: a contractor who holds the permit is the owner’s agent, by written designation or contract, within the limits of their licence.
The second is home warranty. The District’s application package states that proof of third-party home warranty insurance “is required for all new residential construction,” and that permits for that type of construction “cannot be issued prior to receipt of an approved Homeowner Protection Office (HPO) warranty or owner builder approval.” Where neither is in hand at application, the package says the owner or licensed builder signs an undertaking that the permit will not be issued until proof arrives.
So on a new build the builder’s licensing status is not a background detail. It is a condition of issuance.
Schedule C: the signature that makes this concrete
Among the items the District requires with every application is Schedule “C”, the Owners Acknowledgement, which the package describes as “the owner’s undertaking” and as “required for all building permit applications.”
In practice, you sign a document acknowledging the responsibility before the permit exists. The bylaw text above is what that signature points at.
What this means for how you hire
Four practical consequences:
- Put the agency in writing. If your contractor or designer is handling the permit, the bylaw’s own language is “written designation or contract.” Have that document.
- Ask which schedules your project needs, and who signs them. Schedule B for engineered components, Schedule A if there are several professionals, Schedule D for their insurance. If nobody on your team can name them, that is useful information.
- Do not treat permit issuance as a compliance check. Section 1.6 says it is not one.
- Check the package yourself before it goes in. Responsibility sits with you either way, so a read-through is not duplicated effort.
Our list of the gaps that get applications returned at the counter is here: why BC permit applications get sent back. If you want your documents checked against the bylaws before you submit, that is the Permit Readiness Review, with the first analysis free.
This is a plain-language summary of bylaw text, not legal advice.
Frequently asked questions
If the city approved my plans, am I covered?
No. Section 1.6 of the bylaw says issuing a permit, reviewing drawings and inspecting work do not constitute a representation or warranty that the Code or bylaw has been complied with, and that no person shall rely on them as establishing compliance.
Can my contractor take on the responsibility?
Partly, as your agent. The bylaw defines an agent to include a hired tradesman or contractor, representing the owner “by written designation or contract,” within the limits of their licence. The written part matters.
When do I need an engineer or architect?
Where the building official determines that site conditions, size or complexity warrant it, under s. 5.17.1. Two fixed triggers in this bylaw: manufactured products such as trusses need an engineering Schedule B, and a retaining wall over one metre needs professional design and field review.
What is a letter of assurance?
A BC Building Code form on which a registered professional takes responsibility for a defined scope: Schedule B for design and field review, Schedules C-A or C-B for the completion assurance before occupancy, with Schedule A coordinating multiple professionals and Schedule D carrying their insurance proof.